CFO tools · Diagnose
Release sequencing
An order of release for initiatives that respects what depends on what.
A roadmap shows when each initiative finishes. It rarely shows which ones wait for another. This tool records those dependencies and checks the schedule against them.
Each initiative sits in one of four windows, set by its duration: about 6, 12 and 18 months, and 18 to 24 months. There are four windows because there are four duration bands; a finer calendar would claim a precision the durations do not have.
A dependency is declared, never inferred, and each one needs a reason. A hard dependency blocks the plan when its predecessor lands later, lands in the same window, or sits in a circle of hard dependencies. A soft dependency is a preferred order: it is reported and never blocks.
The page also shows the longest chain of hard dependencies and the initiatives no dependency touches. The plan is stored in your browser only.